Officially Opened the First Wind Power Plant in BiH

The first wind power plant in Bosnia and Herzegovina (BiH) became operational eight years after the start of construct was announced on the Mesihovina hill near Tomislavgrad.
Wind-farm Mesihovina will contribute ten percent of the total electricity in the system of the power generator and supplier HZHB. It is made up of 22 wind mills. The construction costs were about €82 million. (Photo: Klix.ba)

The first wind power plant in Bosnia and Herzegovina (BiH) became operational eight years after the start of construct was announced on the Mesihovina hill near Tomislavgrad.

The wind farm is made up of 22 windmills with generators producing more than 165 Gigawatt hours of electricity a year. This is one tenth of the electricity produced by its Mostar-based owner, the electricity generator and supplier EP HZHB.

The project has cost around €82 million. The bulk of it was secured through a loan from the German Development Bank (KfW) which signed a loan contract with EP HZHB worth around €72 million in 2010. The bank also gave €1 million as a grant and EP HZHB provided the remaining money.

Don't want to miss our stories?

Sign up for our newsletter.

Don't want to miss our stories?

Sign up for our newsletter.

The wind farm was supposed to become operational by the end of 2013 and would start paying back the loan. However, due to public procurement issues, the bank agreed to prolong a grace period until the end of 2015.

In 2016, the project finally got its start when EP HZHB and consortium Siemens Wind Power A/S Denmark and Siemens Wind Power LLC Croatia signed a contract about the procurement, delivery and construction of 22 wind turbines worth around €72 million.

The Mesihovina Project was introduced to the public in 2006, and a concession contract with Canton 10 was signed three years later. In 2010 the then president of the BiH Federation Borjana Krišto from Croatian Democratic Union BiH, broke ground for the project on the windy promontory above the Duvno Meadows. After the new management was installed in EP HZHB, led by managers from Croatian opposition parties, the original site was neglected and the project was slowed down.

Megawatts from Wind Power Plants
Investors have announced the construction of several dozen wind power plants over the past few years, but none has actually begun operating.

The Center for Investigative Journalism (CIN) is also available on mobile devices, and you can download the app from the Google Play and App Store.

Tags:

Center for Investigative Journalism is the holder of the certificate

Readers’ support helps CIN reveal corruption and organized crime.
Your donation supports investigative journalism as a public good.

Latest news

Dusko_Radun
FBiH Legislator Duško Radun to Have Mandate Revoked for Second Time Following Court Verdict
The Central Election Commission (CEC) of Bosnia and Herzegovina has revoked Duško Radun’s mandate for the second time in six years due to criminal offenses committed...
Fikret Abdić
Former Mayor of Velika Kladuša, Fikret Abdić, Convicted
The Cantonal Court in Bihać has handed down a non-final conviction to Fikret Abdić for abuse of office, sentencing him to three and a half years in prison and ordering...
NASLOVNA_Ibrahim Hasanagic
Court Rules Following Story on State Secret About Disabled Veterans
The Cantonal Court in Bihać has issued a final ruling stating that CIN caused damage to the reputation of Ibrahim Hasanagić, a wartime disabled veteran from Bihać,...
Load more